以下城市均已開通:
關(guān)閉
當前位置:PMP團購網(wǎng) > PMP考試資料 > 正文

PMP考試練習題及參考答案(22)

轉(zhuǎn)載者:PMP團購網(wǎng)      發(fā)布時間:2012/7/10        點擊: 3650

1. project life cycles provide a better means of measurement of progress and control. the four phases of a project are conceptual development,

  _____, _____, and _____.

  a. preliminary planning, detail planning, closeout

  b. implementation, reporting, termination

  c. development, implementation, termination

  d. execution, reporting, finishing

  e. implementation, termination, post-audit review

  ans: c

  2. response planning is the responsibility of the functional areas and considers

  a. mitigation.

  b. deflection.

  c. contingency planning.

  d. unforeseen occurrences.

  e. all of the above.

  ans: e

  3. the definitive terms of a contract are written during which of the following contract phases?

  a. contract phase

  b. post-award phase

  c. award phase

  d. pre-award phase

  e. requirement phase

  ans: c

  4. the sending or conveying of information from one place to another is the process of

  a. networking

  b. transmitting

  c. interacting

  d. promoting

  e. interfacing

  ans: b

  5. which of the following types of cost are relevant to making financial decisions:

  a. sunk cost

  b. opportunity cost

  c. material cost

  d. a and c only

  e. b and c only

  ans: e

  6. in preparing a good project definition, experienced project managers will:

  a. concentrate mainly on the end product rather than costs or benefits. these come later.

  b. realize that only the “tip of the iceberg” may be showing. as a project manager, you must get beneath it.

  c. understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.

  d. try to convert objectives into quantifiable terms.

  e. all of the above

  ans: e

  7. in which of the following is the cost of risk hidden by the contractor?

  a. firm fixed price contract

  b. fixed price plus incentive

  c. cost plus fixed price

  d. cost plus percentage of cost

  e. a and b

  ans: d

  8. management of a certain building was receiving complaints about slow elevator service. the solution adopted was to add mirrors in the

  lobbies to reduce boredom while passengers waited. this is an example of _____ .

  a. kepner-tregoe method

  b. potential problem analysis

  c. decision analysis

  d. creative problem solving

  e. none of the above

  ans: d

  9. pure risk differs from business risks because pure risk's _____ .

  a. include chances of both profit or loss associated with the business.

  b. include chances of loss and no chances for profit associated with the business.

  c. must incur personal loss with business liability.

  d. must incur business liability associated with loss of pure profit.

  e. b and c

  ans: b

  10. the actual configuration of a pert/cpm network _____ the amount of resources that can be devoted to the project.

  a. increases.

  b. is not affected by

  c. does not require

  d. is heavily dependent upon

  e. is the only means of determining

  ans: d

  11. the following types of costs are relevant to making a financial decision except:

  a. opportunity costs

  b. direct costs

  c. sunk cost

  d. unavoidable costs

  e. none of the above

  ans: c

  12. the standard types of communication include all but

  a. written

  b. verbal

  c. telepathic

  d. nonverbal

  e. none of the above

  ans: c

  13. _____ of the extra costs of the project can often be attributed to a lack of quality.

  a. 0.12

  b. 0.15

  c. 0.2

  d. 0.25

  e. less than 10%

  ans: c

  14. a budget estimate should give the manager cost data accurate to within:

  a. -5 to +10 percent of actual cost

  b. -25 to +75 percent of actual cost

  c. -30 to +75 percent of actual cost

  d. -10 to +25 percent of actual cost

  e. none of the above

  ans: d

網(wǎng)站sitemap

色婷婷激情综合,久久综合九色99,91亚洲精品久久久蜜桃网站,欧美日韩国产美女

PMP團購導(dǎo)航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
主站蜘蛛池模板: 山东| 塘沽区| 南通市| 高碑店市| 中西区| 施甸县| 定兴县| 那曲县| 丹东市| 奇台县| 扶绥县| 新巴尔虎右旗| 祁东县| 玉龙| 吉隆县| 凤阳县| 临夏市| 太康县| 利川市| 德安县| 平和县| 剑河县| 柏乡县| 泸州市| 晋中市| 沁源县| 云阳县| 龙泉市| 五河县| 昌都县| 葵青区| 五峰| 城市| 黎平县| 建昌县| 盈江县| 虹口区| 玉林市| 昌都县| 安远县| 忻州市|