PMP考試練習題(30)

轉載者:PMP團購網(wǎng)      發(fā)布時間:2012/7/17        點擊: 3502

1 Which of the following impacts the critical path?

  A Changing the task duration.

  B Reduce the free float of an activity.

  C Executing a backward pass

  D A or B

  E None of the above.

  ans:A

  2 The range of time allowed for an activity to be completed in is the _____.

  A Planned time (Duration)。

  B Float time (LS - ES, or LF - EF)。

  C Critical time (when ES = LS, or EF = LF)。

  D Scheduled time (LF - ES)。

  E Event.

  ans:D

  3 Free float is the amount of time that an activity may be delayed with out affecting the _____.

  A Early start of the succeeding activities.

  B Late start of the succeeding activities.

  C Project finish.

  D Cost of the project.

  E None of the above.

  ans:A

  4 Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.

  A 0.5

  B 1

  C 1.8

  D 2.2

  E 2.8

  ans:C

  5 In crashing a task, you would focus on:

  A As many tasks as possible.

  B Non critical tasks.

  C Accelerating performance of tasks on critical path.

  D Accelerate performance by minimizing cost.

  E A and D.

  ans:C

  6 Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task

  A 8

  B 8.8

  C 9.1

  D 9.7

  E 10.5

  ans:B

  7 Using the WBS in the Special window, an instance of a work package is:

  A Build house

  B Excavate

  C Prepare Foundation

  D B and C

  E None of the above

  ans:E

  8 All of the following are categories of a milestone in a schedule except:

  A End date.

  B Contract dates.

  C Key events scheduled.

  D Imposed dates.

  E Task duration.

  ans:E

  9 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.

  A Increases.

  B Is not affected by

  C Does not require

  D Is heavily dependent upon

  E Is the only means of determining

  ans:D

  10 Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.

  A Reduce.

  B Eliminate.

  C Double

  D Increase

  E Not affect

  ans:D

  11 The key purpose of project control is to:

  A Plan ahead for uncertainties.

  B Generate status reports.

  C Keep the project on track.

  D Develop the project road map.

  E All of the above.

  ans:C

  12 Fast tracking means to:

  A Speed up a project through parallel tasks.

  B Swap one task for another.

  C Reduce the number of tasks if possible.

  D B and C.

  E None of the above.

  ans:A

  13 As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:

  A Insignificant.

  B Reduced.

  C Unchanged.

  D Increased.

  E Doubled.

  ans:C

  14 The purpose of a dummy activity in an activity-on-arrow diagram is to:

  A Identify a task that could be replaced by another.

  B Take the slack time into account.

  C Show a task that is not necessarily needed.

  D Denote a milestone.

  E Show a dependency relationship.

  ans:E

  15 On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:

  A $-100

  B $100

  C $-150

  D $150

  E 85%

  ans:C

  16 A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:

  A 1.50%

  B 33.00%

  C 75%

  D 67%

  E None of the above.

  ans:B

  17 Resource leveling will often affect the project by making it:

  A Shorter.

  B Longer

  C More responsive to customer needs.

  D A and C

  E B and C.

  ans:B

  18 Using the figure in the Special window, The slacktime in Activity “G” is _____ weeks.

  A 2

  B 3

  C 4

  D 5

  E 7

  ans:C

  19 Using the figure in the Special window, Activity “D” has a latest start time of _____ weeks and a latest finish time of _____ weeks.

  A 2, 10

  B 4, 12

  C 6, 14

  D 7, 15

  E 9, 17

  ans:A

  20 Using the figure in the Special window, Activity “L” has an early start time of _____ weeks and an early finish time of _____ weeks.

  A 11, 13

  B 12, 14

  C 13, 15

  D 14, 16

  E 15, 17

  ans:E

網(wǎng)站sitemap

色婷婷激情综合,久久综合九色99,91亚洲精品久久久蜜桃网站,欧美日韩国产美女

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
主站蜘蛛池模板: 永川市| 罗田县| 永清县| 潜江市| 游戏| 祁门县| 当阳市| 洛南县| 连平县| 长顺县| 辉县市| 广元市| 竹山县| 丰宁| 蚌埠市| 武穴市| 藁城市| 邵武市| 津市市| 文登市| 楚雄市| 偏关县| 西华县| 文登市| 白山市| 公安县| 临汾市| 高雄县| 玉门市| 邵东县| 县级市| 裕民县| 泗洪县| 香河县| 湖北省| 炉霍县| 太谷县| 涞源县| 盘锦市| 金坛市| 兰考县|