以下城市均已開通:
關閉
當前位置:PMP團購網 > PMP考試資料 > 正文

PMP考試題及參考答案(34)

轉載者:PMP團購網      發布時間:2012/7/19        點擊: 5067

1 The following types of costs are relevant to making a financial decision except:

  A opportunity costs

  B direct costs

  C sunk cost

  D unavoidable costs

  E None of the above

  ans:C

  2 Which of the following types of cost are relevant to making financial decisions:

  A sunk cost

  B opportunity cost

  C material cost

  D A and C only

  E B and C only

  ans:E

  3 In which of the following cost estimating techniques are statistics models used:

  A nonparametric cost estimating

  B parametric cost estimating

  C life cycle cost estimating

  D bottom-up estimating

  E All of the above.

  ans:B

  4 Under the terms of 2/10 net 30, the buyer may:

  A deduct 10% of the invoice amount for payment within 30 days

  B deduct 2% of the invoice for payment within 10 days

  C incurs a penalty on 10% for payments more than 30 days late

  D settle the invoice with 2 equal payments; one within 10 days and the other within 30 days

  E None of the above

  ans:B

  5 Which of the following is referred to as payback period:

  A the number of periods required to recover the initial investment

  B the rate of return on the investment

  C the number of periods required to bring project cost back to the original budget, based on current performance

  D loan payment schedule

  E None of the above

  ans:A

  6 Which of the following is referred to as sunk cost:

  A management reserve

  B contingency fund

  C cost budgeted for construction under water

  D expended funds over which there is no further control

  E forecasted budget over-runs

  ans:D

  7 The future value of an annual income flow of $1000 for 2 years at 10% is:

  A $2,200

  B $2,280

  C $2,300

  D $2,310

  E None of the above

  ans:D

  8 The net present value of $110 one year from now at 10% is:

  A $100

  B $120

  C $121

  D $100 less taxes

  E $100 less taxes and interest

  ans:A

  9 Which of the following depreciation methods provides for accelerated depreciation of an asset:

  A Double declining balance.

  B Straight line.

  C Exponential depreciation

  D Double sum of the years digits

  E Double increasing balance

  ans:A

  10 Which of the following is considered a direct cost for producing a widget?

  A The cost of the materials used to produce a widget.

  B The labor costs of the workers who actually produced the widget.

  C The rent for the building in which the widget was manufactured

  D The salary of senior management and the project sponsor

  E A and B only

  ans:E

  11 The reason that cost management is so difficult in project management is that:

  A Projects by definition and nature are non-recurring events and are therefore difficult to predict.

  B There are no tools for identifying project tasks.

  C Project managers do not care about tracking costs, as only schedules are important to all project managers.

  D A and B only

  E B and C only

  ans:A

  12 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

  A Baseline costs

  B Budgeted costs.

  C Estimates upon completion costs

  D Scheduled costs

  E None of the above

  ans:A

  13 The difference between the BCWS and the BCWP is referred to as the:

  A Schedule variance

  B Cost variance.

  C Estimate of completion

  D Actual cost of the work performed

  E None of the above

  ans:A

  14 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

  A Reduce features and/or functionality

  B Increase risk.

  C Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

  D All of the above.

  E A and B only

  ans:D

  15 Typically, during which phase in a project life cycle are most of the project expenses incurred.

  A Concept phase

  B Development of design phase

  C Execution phase.

  D Termination phase.

  E None of the above

  ans:C

  16 What tool have project managers come to use to identify all of the costs associated with a project.

  A A bill of materials

  B A Gantt chart

  C An arrow diagram network.

  D A work breakdown structure.

  E B and C only.

  ans:D

  17 You must produce 27 widgets. You can only produce 9 widgets per production run. Each production line setup costs $1000. Each widget consumes $10 worth of material and $5 worth of labor. What is total variable cost for producing one widget.

  A $1,020

  B $1,010

  C $1,015

  D $20

  E None of the above

  ans:E

  18 You must produce 27 widgets. You can only produce 9 widgets per production run. Each production line setup costs $1000. Each widget consumes $10 worth of material and $5 worth of labor. What is the total fixed cost for producing the widgets.

  A $3,000

  B $27,000

  C $27,270

  D $1,335

  E $1,000

  ans:E

  19 In a contract, the point of total assumption refers to the point where:

  A The customer incurs the total financial responsibility for each additional dollar spent.

  B The contractor incurs the total financial responsiblity for each dollar spent.

  C The schedule and cost variance are zero.

  D The customer will incur no further costs for the work the contractor performs in the completion of the contract.

  E B and D only.

  ans:E

  20 The salvage value of an asset is:

  A The value of the scrap metal if a new asset were taken to a scrap yard.

  B The value that an asset has on the books after one year of depreciation.

  C The costs that have been sunk into the project to date.

  D The expected cash value at the end of an assets useful life.

  E A and D only.

  ans:D

色婷婷激情综合,久久综合九色99,91亚洲精品久久久蜜桃网站,欧美日韩国产美女

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
主站蜘蛛池模板: 瑞昌市| 阿拉善左旗| 同江市| 土默特右旗| 三门县| 乳山市| 琼结县| 华亭县| 绵阳市| 白山市| 定安县| 遂平县| 郧西县| 磴口县| 星子县| 平湖市| 襄垣县| 定安县| 若尔盖县| 榆树市| 渭南市| 巴彦县| 高安市| 太湖县| 孙吴县| 兴安县| 习水县| 敖汉旗| 江油市| 石嘴山市| 昭觉县| 盖州市| 宿迁市| 铁岭县| 开封市| 兰考县| 惠安县| 大姚县| 宁都县| 太和县| 桐庐县|