第5章PMP練習題(含答案-PMP考試題系列 )
1.A new project manager is planning a complex hardware installation project. The team consists of 13 people who are experts in their fields. The project manager does not want to micromanage the project. How far should he decompose the work? 參考答案:D 2.The customer wants to make a major change to the scope of work when the project is mostly complete. The project manager should? 參考答案:B 3. A client has asked you to add scope of work to the project. The project is under budget and a little ahead of schedule. What should you do? 參考答案:B 4.The project is mostly complete. However, the customer wants to make a major change to the scope of work. The project manager should: 參考答案:B 5.A key attribute of validating scope is: 參考答案:B 6.Validate Scope 參考答案:D 7.Project scope: 參考答案:C 8.At the end of a project, a project manager determines that the project has added four areas of functionality and three areas of performance. The customer has expressed satisfaction with the project. What dose this mean in terms of success of the project? 參考答案:B 9.A project manager is in the process of validating scope of a deliverable with the customer. What is the MOST important thing the project manager should ensure? 參考答案:C 10.The process of creating a work breakdown structure results in? 參考答案:B 11.Your customer asked you to perform some additional tasks that are not included in the formal contract.You should: 參考答案:A 12. You are assigned as a project manager to lead a new quality improvement project. Management is asking for a plan. Which of the following should you create FIRST? 參考答案:A 13.Scope decomposition involves subdividing the major project deliverables into smaller pieces to: 參考答案:A 14.A key reason to use a work breakdown structure is to 參考答案:D 15. A project manager is concerned abort the amount of gold plating that has been occurring on past project. All the following would not be of use in controlling gold plating EXCEPT: 參考答案:C 16. The construction phase of a new software product is near completion. The next phase is testing and implementation. The project is two weeks ahead of schedule. What should the project manager be MOST concerned with before moving onto the final phase? 參考答案:A 17. You recently finished working on a project team that required extensive overtime to meet a demanding schedule. Although the initial tasks involving computer design were a good fit for you, you also were required to produce numerous technical documents and to perform several programming tasks. The tasks involving technical documents and programming were not a part of your original assignment and were not in your area of expertise. You had to work many weekends and nights to get everything done. You wondered why you had to do the work and why it was not assigned at the beginning of the project. You are managing the company’s next project and want to avoid a similar situation. Therefore, you should: 參考答案:A 18.Sponsor decreased the Project funding significantly. What is the alternative? 參考答案:B 19.A WBS is BEST described as a tool for tracking: 參考答案:D 20.Your customer signed off on the requirements definition document and scope statement of your video game project last month. Today she requested a project scope change. She would like to make it an interactive game that can be played on a person's television and on a computer. This represents a scope change that, at a minimum 參考答案:A 21.A work package is a 參考答案:A 22. When training new project team members, you were asked what should be done during validating scope, your answer should be: 參考答案:C 23. System analysis/engineering, value engineering and value analysis are all examples of? 參考答案:C 24. These two processes in the Controlling process group are performed in parallel to assure correctness and acceptance of the work. Which are they? 參考答案:C 25. Which of the following is an important input to validate scope? 參考答案:A 26.Who rarely request changes to the project scope? 參考答案:A 27. A deliverable fails to give expected results, but was formally accepted by the customer. Which of the following best describes the activity involved? 參考答案:D 28. Just assigned as a Project Manager to a new petrochemical facility construction project and have been given the completed project scope, you will first: 參考答案:B 29. The project is completed and the final deliverable has been sent to the customer, but the customer refuses to give final acceptance on the project. It is most important for the manager to: 參考答案:C 30. You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following? 參考答案:C 31. Validate scope should be done? 參考答案:C 32.Which of the following is correct in regard to scope change control? 參考答案:C 33. The tool that provides a basis to identify the work that must be scheduled is the 參考答案:C 34.The product scope is measured against the ( ), 參考答案:C 35.Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name of this identifier? 參考答案:D 36.( ) contains detailed descriptions of work packages. 參考答案:A 37. All of the following are inputs into Create WBS EXCEPT: 參考答案:A 38.You are asking R&D staffs to lower you sots but with the same exact scope of work. Your staff will firstly- 參考答案:B 39.The preparation of the scope baseline involves the: 參考答案:C 40. During the execution phase of the project, you realized the subcontractors are working with incomplete and different scope statements. As the project manager, what should you do FIRST: 參考答案:A 41. 下述關于WBS 的說法,正確的是? 參考答案:C 42. 當一名團隊成員為工作包定義活動時,找到你說目前信息不足,不能分解成具體的活動。你指示該成員,把工作包分解到里程碑的水平。這體現了? 參考答案:C 43.在以下情形需要修訂WBS: 參考答案:A 44. 在什么階段會參考需求跟蹤矩陣? 參考答案:D 45.You are having difficulty estimating the cost of a project. Which of the following BEST describes the most probable cause of your difficulty? 參考答案:A 46. What is the WBS typically used for? 參考答案:B 47.Starting from formal scope change request by an internal stakeholder,a project manager has taken scope change control process.What is the next step? 參考答案:D 48. During planning, a project manager discovers that part of the scope of work is undefine What should the project manager do? 參考答案:B 49.Two people on the same project team have just found out they are working on the same scope of work. This is an example of a lack of: 參考答案:A 50. 在以下哪一個項目管理過程組用到需求跟蹤矩陣? 參考答案:C |