第8章PMP練習題-第三部分(PMP章節輔導)
21 A. project team is in the design stage of a new mountain bike prototype. The team is in the process of identifying which type of frame and material will provide high performance at a low cost .Which of the following is the MOST likely technique used to determine these variables? 22.The principal use of a Pareto diagram is to: 23.Statistical sampling is a method to determine the conformance to requirements for some element or product of a project. Its greatest advantage is that it: 24.From the project perspective, quality attributes: 25.You are asked to select tools and techniques to implement a quality assurance program to supplement existing quality control activities. Which of the following would you choose? 26.A project manager is worried about the costs on the project. There is a lot of rework and scrap and inventory costs are rising. If you were a mentor to this project manager, what is the BEST advice you could offer? 27.Which of the following approaches to quality improvement is least likely to produce positive results? 28.The statistical control chart is a tool used primarily to help 29. A project team has invited many of the project stakeholders to help them inspect quality on the project. Which of the following would NOT be an output of this activity? 30. Your project has had a major defect and you have gotten the project team and the quality engineers involved in problem analysis. There are three different opinions |