11.Based on historical data, the amount of overtime associated with the design effort of a project is estimated at 100 hours with 0.40 probability, 200 hours with 0.40 probability, and 300 hours with 0.20 probability. What is the expected value of the amount of overtime? 12. Additional risk response development is needed when the—— 13.If a risk event has a 90% chance of occurring, and the impact will be US $10,000, what does US $9,000 represent? 14.Projects are particularly susceptible to risk because 15.What does the standard deviation have to do with risk? 16.During execution a major problem occurs that you did not include in your risk management plan, you should 17. You are in the middle of project execution and find that you are running out of money due to unanticipated changes. What is the BEST thing to do? 18. You are performing an audit of one of your project manager’s projects and notice that she did not consider the network diagram as part of the risk identification process. Which one of the following is the BEST explanation for this situation. 19. Your team has identified a possible positive outcome from your project. Management assigns the most senior staff to make sure that component is developed as quickly as possible. This is an example of: 20.Contingency planning involves: |