第12章PMP練習題-第一部分(PMP考試復習試題)
1.You are the project manager for an outdoor concert event scheduled for 1 year from today. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You've decided to contract with a professional services company that specializes in writing custom software programs. You want to minimize the risk to the organization, so you'll opt for which contract type? 2.Contract type selection is dependent on the degree of risk or uncertainty facing the project manager. From the perspective of the buyer, the preferred contract type in a low-risk situation is 3.A purchase order is a good example of which form of contracting? 4.A contract for undefined work 5.A project manager for a large manufacturing concern is working on a project that calls for a new building to be constructed to house a new clean system manufacturing process that is critical to the success of the project. Construction is not a core competency of his company. His team has the ability to create a detailed SOW with penalties if specific statements of work deliverables are not meet. He is in procurement planning evaluating which contract would work the best. Which of the following is BEST type of contract for this situation? 6.The primary objective of incentive clauses in a contract is to: 7.You are trying to decide whether to lease or buy an item for your project. The daily lease cost is US $150. To purchase the item, the investment cost is US $2,000 and the daily cost is US $50. In how many days will the lease cost be the same as the purchase cost? 8.Which contract type consists of Target Cost, Profit, Ceiling Prices, and shared ratio or risk? 9 . Of the following, the contract type with the highest cost risk for the contractor is: 10.A legally binding document offered unilaterally is |