第12章PMP練習題-第四部分(PMP項目管理認證)
31.A project manager for a large international bank has a project team that just implemented an electronic funds project involving four large vendors. The project manager struggled through every phase of the procurement process since the bank had a weak internal contracts department. What would be the MOST appropriate thing to do to ensure the problems are resolved for future projects? 32. You are working on a complex procurement. You must reach agreement with the seller about numerous items including responsibilities and authorities,applicable terms and conditions,contract financing,technical and business management approaches,and price before signing the contract. You scheduled a negotiation session. The seller will have eight representativest at the session; you will have ten. Because this procurement is so complex, contract negotiation should be handled____ 33. You need to use suppliers to provide several different products and services for your project. You want to create a document to describe the work in enough detail to allow prospective sellers to bid on them. What document should you create? 34. You have decided to terminate a contract because you no longer need the work from the seller. What is the BEST way to communicate this to the seller? 35.Your seller on the project has not performed and you are terminating the contract. Which of the following is the BEST thing to do? 36. While completing a project, a worker strike in the seller’s city has resulted in the required deliverable being late. What is generally the BEST thing for the 37.A customer has requested a change that requires you to obtain new equipment. You need to decide whether to lease or buy the equipment. The daily lease cost is US $150. The cost of purchasing the item is US $2,000 for the investment cost and US $50 for the daily cost. You will need to use the item for about 12 days. What should you do? 38.Once signed a contract is legally binding unless: 39.In some cases, contract termination refers to 40.You are a contractor for a state agency. Your company recently completed a water resource management project for the state and received payment on its final invoice today. A procurement audit has been conducted. Formal notification that the contract has been closed should be provided to your company by the- |