1. What are the best uses of PERT?
A. Used in the planning phase to do “what if” for the project
B. Assist in the controlling of changes to the project
C. Is used in the process of preparing a WBS for the project
D. To measure future consequences of activities
E. A andD
計劃評審技術的最佳用途是什么?
A. 在項目計劃階段用于對假定情況的推測
B. 幫助控制項目中的變更
C. 用來準備項目的工作分解結構
D. 來衡量活動的未來結果
E. A 和D 2. Milestones established by the customer must be adhered to by:
A. Project manager
B. Functional managers
C. The customer
D. BothAandB
由客戶建立的里程碑必須贏得____ 的支持
A. 項目經理
B. 職能經理
C. 客戶
D. A 和B
3. The decision to request an increase the resources for a project is the responsibility of the:
A. Functional manager
B. Project manager
C. Director of project management
D. Customer
申請增加項目資源的決策是_____ 的責任?
A. 職能經理
B. 項目經理
C. 項目經理的主管
D. 客戶
4. In which of the following project phases is the project scheduled developed?
A. Conceptual
B. Planning
C. Implementation
D. Design
E. Production
在下面哪個階段制定項目進度?
A. 概念
B. 計劃
C. 實施
D. 設計
E. 生產
5. Once the durations of the activities are calculated for a completed network, a forward pass and a backward pass will provide:
A. the float of the activities
B. the early start and late start only
C. the critical path
D. AandC
在一個完整的網絡圖中,活動的工期計算出來后,正推法和反導法將提供:
A. 活動的浮動時間
B. 只有最早開始和最晚完成
C. 關鍵路徑
D. A 和C
6. Which of the following CANNOT be tracked using the WBS?
A. Time
B. Cost
C. Quality
D. Amount of work
下面哪個不能用工作分解結構來跟蹤?
A. 時間
B. 成本
C. 質量
D. 工作量
7. To crash a scheduled you should:
A. increase the time allowed on those tasks that have float
B. try to increase expenditures of time on only those tasks that are behind schedule
C. replace those workers that are not performing up to par with the busy workers
D. increase work efforts on those tasks that are on the critical path
要趕進度,你應該:
A. 增加那些有浮動時間的活動的工期
B. 試著增加那些進度落后的任務的開銷
C. 替換那些沒有與他們同等工人忙碌的工人
D. 增加那些在關鍵路徑上的任務投入
8. Which of the following is NOT one of the primary needs for good project scheduling?
A. Cutting costs and reducing time
B. Decreasing the time required for decision making
C. Eliminating idle time
D. Development better trouble shooting procedures
下面哪些不是好的項目進度安排的基本需求?
A. 減少成本和時間
B. 減少決策的時間
C. 消除空閑時間
D. 制定很好的問題解決流程
9. The time necessary to complete a project is referred to as:
A. implementation time
B. life cycle
C. operations cycle
D. production cycle
完成項目所需的時間是指:
A. 實施的時間
B. 生命周期
C. 運作周期
D. 生產周期
10. The successful project managers spend most of their time:
A. planning with their personnel
B. planning with top management
C. communicating with the project team
D. studying project results
成功的項目經理把他們的大部分時間花在:
A. 與他們的職員作計劃
B. 與高層管理作計劃
C. 與項目團隊進行溝通
D. 研究項目結果
PMP考試試題參考答案:1-5 EDBBD 6-10 CDDBC