PMP考試題庫之項目質量管理6-10題:6. A group frequency distribution of a set of observations is:
A. The number of observations in the group
B. The frequency divided by the total number of observations
C. An arrangement which shows the frequency of occurrence of the values of the variable in ordered classes
D. A useful picture of the way in which the quality of a product has varied in the past
E. C andD
一組觀察的頻率分布是:
A. 觀察的數量
B. 頻率除以總的觀察數量
C. 在有序級中變量變化狀況的排列情況
D. 是一個有用的圖示方法,表示產品質量過去發生的變化
E. C 和D
7. The primary components of the quality management function are:
A. Quality planning
B. Quality control and assurance
C. Quantitative measurement
D. Qualitative assessment of the product
E. A andB
質量管理功能的基本組成是:
A. 質量計劃
B. 質量控制和保證
C. 定量衡量
D. 產品的定性評估
E. A 和B
8. Setting the number of defects before the lot is rejected, is a direct responsibility of
A. A functional worker
B. The project manager
C. Management
D. The accounting department
在拒收一批產品之前設置次品數量的工作是誰的直接責任?
A. 職能部門的工作人員
B. 項目經理
C. 管理層
D. 會計部門
9. Which of the following has the greatest effect on a product’s reliability and maintenance characteristic?
A. Conceptualization
B. Product design
C. Fabrication
D. A andB
下面哪些對產品的可信度和維護特性有最大的影響?
A. 概念化
B. 產品設計
C. 生產
D. A 和B
10. On a project the project manager should strive for a “Quality Level” that:
A. is the highest level possible
B. is as close to the project objective as possible
C. represents the least cost to the project
D. exceeds the specified requirements of the project
E. A andD
在一個項目中,項目經理會盡量爭取怎樣的一個“質量水平”?
A. 盡可能最高的
B. 盡可能貼近項目目標
C. 最少的項目成本
D. 超過項目已定義的需求
E. A 和D
PMP認證考試題參考答案: 6-10 EECDB