PMP考試題庫之項目人力資源管理1-5題:1. What would one expect to occur when a functional organizational structure is used in a multiple project environment?
A. One individual will be directly responsible for each project
B. Project members will place more emphasis on their functional specialty than on the objectives of the project
C. The response to customer needs is slow
D. BothBandC
在多項目的環境下采用職能型組織結構時,一般將發生什么?
A. 一個個體直接負責一個項目
B. 項目成員將更強調他們的職能專業,而不是項目的目標
C. 對客戶需求的反映比較慢
D. B 和C
2. When the primary concern of a company is to have a project environment that enables the project team members to work in a synergistic manner, while still maintaining a functional environment that facilitate technological growth, the most appropriate organizational structure to use is a:
A. Traditional organization
B. Matrix organization
C. Pure projectized organizational structure
D. BothBandC
公司的首要關注是能夠營造一個使項目成員保持一種精力充沛工作的項目環境,同時保持一種能夠促進技能提高的職能型的環境,下面選項中最合適的組織結構是:
A. 傳統型的組織結構
B. 矩陣型的組織結構
C. 純項目型的組織結構
D. B 和C
3. Which of the following is NOT a characteristic of the pure projectized organizational structure?
A. There is a lack of opportunity for technical interchange between projects
B. There may be duplication of facilities and an inefficient use of resource
C. There is a complete line of authority over the project
D. Limited span of control
下面哪個不是純項目型的組織結構的特征?
A. 項目間缺乏技術交流的機會
B. 資源使用的低效率以及設備的重復配置
C. 完整的項目授權體系
D. 有限的控制范圍
4. A pure matrix organizational form:
A. is the most efficient for the initial definition of policy and procedures
B. has the least amount of conflict
C. allows for shared authority and responsibility
D. Reduce duplication of effort
一個純的矩陣型的組織架構是:
A. 對政策和程序的初始定義是最有效率的
B. 沖突最少
C. 允許分享權力和義務
D. 減少重復的投入
5. In the project expediter form of project management the project expediter:
A. has the authority to make most of the decisions relating to the project
B. assures the timely arrival of parts/materials and completion of tasks
C. has ultimate responsibility for the project
D. controlling of resources remains the most critical
在項目管理的項目聯系員形式中,項目聯系員:
A. 有權對于項目相關絕大部分事情做出決策
B. 確保材料或部件及時送達及任務的完成
C. 對項目負有最終的責任
D. 控制資源是最為關鍵的
PMP認證考試題參考答案: 1-5 DBDDB