PMP考試題----項目人力資源管理題目11-15:11. In order for project managers to be effective, they must:
A. Continue to be actively involved in their technical field of expertise
B. Actively participate with other management personnel in planning the project
C. Monitor and control all task of the project to the lowest level of the WBS
D. Control the functional manager’s personnel on all project aspects
為了使項目經理的工作更有效,他們必須:
A. 繼續(xù)熱情的專注于專業(yè)技術領域
B. 主動與其他的管理人員一起編制項目計劃
C. 檢查控制WBS 最底層的所有工作
D. 控制項目的各個方面職能型經理下屬的人員
12. What is the process that the project manager uses to coordinate the efforts of workers toward the accomplishment of group(project) goals?
A. Integration of skills
B. Procurement management
C. Leadership
D. Problem solving
為了努力完成項目目標,項目經理經常用來協調項目人員投入的過程是什么?
A. 整合技能
B. 采購管理
C. 領導能力
D. 解決問題的能力
13. Which of the following is NOT critical action for the project manager to take in the integration process for a matrix organization?
A. Planning for integration
B. Development of an integrated WBS, schedule, and budget
C. Provide technical training for the project team members
D. Resolve customer problems
項目經理在對矩陣型組織實施一個整合過程時,下面的哪個做法不是關鍵的:
A. 整合計劃
B. 制定集成的WBS,日程安排和預算
C. 為項目成員提供技術培訓
D. 解決客戶的問題
14. Which of the following is NOT a form of power that the project manager can use due to the position of project manager in the company?
A. Formal
B. Reward
C. Penalty
D. Expert
在公司里,下面哪個不屬于項目經理在其職位上可以行使的權力?
A. 正式的權力
B. 獎勵權
C. 處罰權
D. 專家權
15. Which of the following is NOT an organizational form?
A. Functional organization
B. Matrix organization
C. Projectized organization
D. Project expediter
下面的哪個不屬于組織的形式:
A. 職能型組織
B. 矩陣型組織
C. 項目型組織
D. 項目聯絡人
PMP考試題的參考答案: 11-15 BACDD