項目溝通管理-PMP考試題目(1-5題)1. Which of the following can cause a communication border?
A. Differing perceptions as to project goals and objectives
B. Insufficient action on the part of the project manager
C. Competition for facilities, equipment, material, manpower, and other resources
D. Personality conflicts between managers and/or other personnel
E. Resistance to change
F. All of the above
下面哪一項會引起溝通障礙?
A. 對項目目標和目的的不同理解
B. 項目經理方面行動的不充分
C. 設施、設備、材料、人力和其他資源的競爭
D. 在經理和/或其他員工之間的個人沖突
E. 對變化的抵制
F. 以上所有
2. Most of the project manager’s external communication links consist of:
A. written documents
B. oral communications
C. tactile contact
D. informal contact
項目經理的大多數外部溝通的聯系是由下面哪項組成的:
A. 書面的文檔
B. 口頭的溝通
C. 戰術聯系
D. 非正式的聯系
3. The internal communication linkage are the most important to the health of the project. Which of the following is one of the major driving forces for effective communication in a project?
A. Optimization
B. Differentiation
C. Selection
D. Integration
內部溝通的聯系對于項目的良性運作是最重要的。下面哪點是項目有效溝通的主要驅動力之一?
A. 優化
B. 差異化
C. 選擇
D. 整合
4. The critical element in a project’s communication system is the:
A. progress report
B. project directive
C. project manager
D. customer
在項目溝通系統中的關鍵因素是:
A. 進展報告
B. 項目指示
C. 項目經理
D. 客戶
5. System integration consists of:
A. assuring that the pieces of a project come together at the right time
B. planning for contingencies that may occur throughout the life cycle of the project
C. the pieces of the project function as an integrated unit
D. A andC
系統整合包括:
A. 確保項目的每一部分在適當的時候集中在一起
B. 制定在項目生命周期中可能發生的應急計劃
C. 項目的各個部分以一個整體運作
D. A 和C
PMP參考答案(溝通管理): 1-5 FADCD