項目風(fēng)險管理--PMP考試章節(jié)練習(xí)(1-5題)1. Risk management includes the processes concerned with_______, __________, and _________ uncertainties during the project’s life cycle.
A. Utilizing, supporting, and determining
B. Quantifying, controlling, and monitoring
C. Analyzing, monitoring, and response initialization of
D. Costing, planning, and constraining
E. Identifying, analyzing, responding to
風(fēng)險管理包括________ 、_________ 和__________ 在項目的生命周期里的不確定性:
A. 利用、支持和判斷
B. 質(zhì)化、控制和監(jiān)控
C. 分析、監(jiān)控和對啟動反應(yīng)的
D. 成本、計劃和限制
E. 識別、分析和應(yīng)對
2. PMI states that there are two risk types: business and insurable. Which of the following are considered are considered insurable risks?
A. Employee replacement costs
B. Opportunity cost
C. Sunken costs
D. Damage caused by a bonded contractor
E. A andD
PMI 認(rèn)為存在兩種類型的風(fēng)險:商業(yè)的和可保險的。下面哪個被認(rèn)為是可保險的風(fēng)險?
A. 員工替換成本
B. 機會成本
C. 沉淀成本
D. 由債券作擔(dān)保的承包商引起的損失
E. A 和D
3. The three attributes of project risk are________, _________, and ________.
A. What might happen, who it happens to, and how much will it cost
B. Notification, frequency of relevant events, probability of occurance
C. Risk cost, quality, control
D. Quality, risk planning, total number of risk events
E. Risk event, probability occurrence, the amount at stake
項目風(fēng)險具有三個屬性:__________ 、___________ 和___________ 。
A. 可能發(fā)生什么,對象是誰以及花費多少成本
B. 通知,相關(guān)事件的頻率性和時間發(fā)生的可能性
C. 風(fēng)險的成本,特征和控制
D. 質(zhì)量、風(fēng)險計劃、風(fēng)險事件的全部數(shù)量
E. 風(fēng)險事件、發(fā)生的可能性、風(fēng)險發(fā)生后所帶來的價值
4. A risk is defined as what might happen to the_______ of the project
A. assessment
B. detriment
C. schedule
D. cost
E. scope
風(fēng)險事件被定義為發(fā)生在項目__________
A. 評估
B. 損害
C. 時間安排
D. 成本
E. 范圍
5. When is the project’s amount at stake the lowest?
A. Conceptual
B. Design
C. Close-out
D. Implementation
什么時候項目的風(fēng)險所導(dǎo)致的代價最低:
A. 概念
B. 設(shè)計
C. 收尾
D. 實施
PMP考試練習(xí)答案(風(fēng)險管理):1-5 EEDBA