項目風險管理-PMP考試章節練習(11-15題)11. The project budget has been finalized. Additional work has been discovered that was not planned for in the budget or project scope. Where could the funds be found to cover the newly discovered work item?
A. Contingency reserve
B. Project profit
C. Management reserve
D. Abandoning fund
項目預算已經完成。但是發現有額外的工作沒有計算到預算或項目范圍中。在什么樣的資金能夠包含最近發現的工作內容?
A. 應急備用金
B. 項目利潤
C. 管理備用金
D. 廢棄資金
12. As a means of deflecting project risk, the project manager should consider:
A. not implementing the project
B. the use of another project manager
C. establishing a sunk cost fund
D. ignoring the risk
E. insurance whenever possible
作為風險轉移的一種方法,項目經理應該考慮:
A. 不實施項目
B. 啟用另一個項目經理
C. 建立沉淀資金
D. 忽略風險
E. 需要時上保險
13. Which phase of the project life cycle has the highest uncertainty?
A. Conceptual
B. Planning
C. Design
D. Implementation
E. Termination
項目生命周期中哪個階段有最大的不確定性?
A. 概念
B. 計劃
C. 設計
D. 實施
E. 中止
14. Which of the following fit the category of external risks?
A. Project delays, budget underruns, movement of city utilities
B. Regulatory, currency changes, taxation
C. Natural disasters, regulatory, design
D. Inflation, design, social impact
E. Political unrest, budget overruns, size and complexity of the project
下面哪種分類屬于外部風險?
A. 項目延遲,預算超支,城市設施的遷移
B. 規章制度,貨幣變化,稅收
C. 自然災害,規章制度,設計
D. 通貨膨脹,設計,社會方面的影響
E. 政治動蕩,預算超支,項目的大小和復雜性
15. In the area of legal risks, there are two reasons for licensing of projects. One reason is for revenue generation by the community: the other is for:
A. harassment of the project manager
B. bureaucratic interest in the project
C. public safety of the product
D. monitoring of the project schedule
E. identification of the project manager
在法律風險方面,有兩個原因給項目發許可證。一個是收益由公眾產生,另外一個是:
A. 不讓項目經理閑著
B. 官僚的原因
C. 產品對公眾的安全
D. 項目進度的監測
E. 項目經理的識別
PMP考試練習答案(風險管理):11-15 CEABC