PMP考試題庫--項目風險管理(16-20題)

轉載者:PMP團購網      發布時間:2014/11/11        點擊: 3409

項目風險管理-PMP考試章節練習(16-20題)

16. Decision trees are best used for:
A. determining the interaction of the amount at stake and the expected value
B. association of the probabilities with the risk events
C. an illustration of how to see the interactions between decisions and the associated events
D. a flow chart which determines the standard deviation of the risk event

決策樹的最佳用途是:
A. 確定風險所帶來的損失和預期的風險情況下獲得利潤之間的關系
B. 風險事件之間的概率關系
C. 一種展示決策和相關事件之間關系的圖形化的方法
D. 一種流程圖用來確定風險事件的標準偏差

17. Contained within the first step of a five step process to determine the risk analysis of the project’s risk events, a process of ________ is performed to see if the risk should be included or excluded as part of the project scope
A. determining the probability
B. contingency effort
C. assessing the consequences and severity
D. screening

在五個用來確定項目風險事件的分析過程的第一步中,__________ 的流程的執行是為了確定風險是否包括在項目范圍的一部分中。
A. 確定概率
B. 應急投入
C. 評估結果和嚴重度
D. 篩選

18. A project of 2 million has an adverse event that has probability of 50% of occurrence and a potential loss of $20,000. This represents an expected negative value of:
A. $100,000
B. $1,000
C. $100
D. $10,000

一個兩百萬美元的項目有50%的可能會損失20000 美元。這表示預期的不利損失是:
A. 100000 美元
B. 1000 美元
C. 100 美元
D. 10000 美元

19. The assigned values of risk for a project is best accomplished through a structured methodology that ensures all project elements are evaluated. The project tool that is best suited for the structured analysis of the project risk is the:
A. contract
B. specification
C. statement of work
D. work breakdown structure
E. network programming diagram

給項目賦予風險值最好是通過一個結構化的方法完成,此方法能保證所有的項目元素都進行了評估。最適合這種結構化風險分析的工具是:
A. 合同
B. 規范
C. 工作說明
D. WBS
E. 網絡計劃圖

20. The total amount of risk that is calculated for a project is found by:
A. multiplying the sum of each the risks times the amount at stake
B. calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events
C. cannot be calculated since all risks are not known
D. the amount of project reserves available

項目風險總值的計算是:
A. 各個風險的總和乘以其所帶來的價值
B. 計算各個風險的概率乘以其所帶來的結果的價值的總和
C. 不能計算出來,因為所有的風險都不知道
D. 項目可用備用金的金額

PMP考試練習答案(風險管理):16-20 CDDDB

閱讀本文的人還閱讀了:
PMP認證為什么這么火爆?
沒做過項目經理可以考PMP嗎?
PMP報名時間是哪天?
PMP考試試題是什么樣?
PMBOK是什么?

色婷婷激情综合,久久综合九色99,91亚洲精品久久久蜜桃网站,欧美日韩国产美女

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
主站蜘蛛池模板: 荆门市| 弥渡县| 西峡县| 松溪县| 阜新市| 辽阳市| 梁山县| 饶阳县| 汉沽区| 芜湖市| 佳木斯市| 云龙县| 桦南县| 浦东新区| 灵武市| 酉阳| 祁连县| 通江县| 荆门市| 凤山市| 腾冲县| 绥棱县| 阳原县| 即墨市| 于田县| 买车| 曲靖市| 海阳市| 井陉县| 梓潼县| 顺义区| 卢氏县| 江门市| 六安市| 开封县| 郓城县| 莱阳市| 乌鲁木齐市| 大庆市| 冀州市| 沙湾县|