合同與采購管理-PMP考試章節練習(21-25題) 21. A contractor is hired on a CPFF basis. The estimated cost of the contract is $100,000; however, at completion the contract costs total $125,000. The agreed upon percentage profit paid to the contractor is 15%. How much will the contractor receive? 承包商在CPFF 的條件下受雇,合同估計的成本是$100,000,但是項目實際完成時花費了$125,000 。已經同意的支付給承包商的利潤率是15%。承包商將得到多少? 22. A contractor is hired to construct a storage shed. The performance cost is $1,500, with $6,500 in materials, and a 50% incentive fee. The contractor completes the storage shed in 130 hours, with a materials cost of $6,200. The contractor is paid $7,850 at completion. What type of contract is being used for this project? 一個承包商受雇建造一個存貨倉庫。執行成本是$1,500,原料是$6,500,以及50%的激勵酬金。承包商完成工程用了130 個小時,消耗了$6,200 的材料。在完工時,承包商獲得$7,850 的報酬。這個項目中使用了哪種合同形式? 23. A company is going into the procurement on a project and must decide what type of contract to use. This decision is made in what phase of the Acquisition Process? 公司在項目中即將開采采購并且必須決定采用何種合同形式,這一決定是在采購過程的那個階段作出? 24. When a project’s contract is not fully executed caused by a direct fault of the seller, the owner is entitled to seek damages. What condition best describes this occurrence? 當項目合同由于賣方直接過錯而未能完全履行時,業主有權尋求賠償金。哪個條款最好地描述了此種情形? 25. Administrative closure should take place: 項目管理收尾應該發生在: PMP考試練習答案(合同采購):21-25 ADABE |