PMP考試每天一練-2022年PMP考試模擬題113
PMP考試練習題一: 項目目前處于執行的中間階段。項目落后于進度,而且面臨成本超支的問題。在這個時候,客戶提出變更現有需求的請求。項目經理應該采取下列哪一項措施? A project is in the middle of execution. The project is running behind schedule and faces cost overruns. During this period, the customer requests a change to existing requirements. The project manager should do which of the following action? A:與團隊成員討論當前版本是否允許變更 Discuss with the team member whether or not the change can be accommodated in the current release. B:立即開始變更工作,節省時間和成本。 Start to immediately work on the change to save time and cost. C:確保變更已用文件記錄,并遵循正式的變更流程。 Ensure that the change is documented and the formal change process is followed. D:分析成本和進度影響,并通知客戶。 Analyze the cost and schedule impact and inform the customer. PMP考試答案解析:4.6實施整體變更控制-引言。“項目的任何人都可提出變更請求,可以口頭,但必須書面記錄,并納入變更管理和配置管理系統中。” PMP考試參考答案:C PMP考試練習題二: 下列哪項不是整體變更控制的內容 A.對可能引起變更的因素施加影響 B.在整個項目期間和整個范圍內協調各種類型的變更 C.確保項目的績效測量基準不發生變化 D.當變更實際發生時對變更進行管理 PMP考試參考答案:C |