PMP考試每天一練-2023年P(guān)MP考試模擬題26
PMP考試練習(xí)題一: 由于一臺設(shè)備設(shè)計規(guī)格中的某一項被忽略了而導(dǎo)致項目延期,而趕制此項需要更長的交貨期。為避免這種情況的發(fā)生,項目經(jīng)理在項目規(guī)劃期間應(yīng)完成下列哪一項? A project is delayed because one item in the equipment specification has been ignored. It will require a longer lead time to catch up. To avoid this situation, the project manager should have done which of the following in project planning? A:A 制定應(yīng)急計劃 prepare a contingency plan B:選擇更為可靠的供應(yīng)商 select a more reliable supplier C:在識別風(fēng)險過程上花費更多的努力 spend more efforts on the process of risk identification D:確保該項不在關(guān)鍵路徑上 ensure that the item is a not on the critical path PMP考試答案解析:所屬過程組:規(guī)劃過程組。所屬知識領(lǐng)域:項目風(fēng)險管理。出現(xiàn)這種情況識別風(fēng)險不充分。 PMP考試參考答案:C PMP考試練習(xí)題二: 以下哪項不是用于進(jìn)度控制的工具或技術(shù)? A.偏差分析 B.三點估算 C.假設(shè)情景分析 D.資源平衡 PMP考試參考答案:B |