PMP考試題庫(kù)之項(xiàng)目成本管理6-10題:6. Cost Variance (CV) is which of the following equations?
A. CV= BCWP – BCWS
B. CV= BCWP –ACWP
C. CV= SV/BCWS
D. A andC
成本偏差(CV)是下面的哪個(gè)公式?
A. CV= BCWP – BCWS
B. CV= BCWP –ACWP
C. CV= SV/BCWS
D. A andC
7. In the following table, which project is most likely to finish ahead of schedule? Project BCWS BCWP ACWP
A 1000 800 600
B 1000 600 800
C 1000 1200 800
A. Project A
B. Project B
C. Project C
D. All three the projects will be completed at the same time
下面的表中,哪個(gè)項(xiàng)目最可能會(huì)提前完成?
A. 項(xiàng)目A
B. 項(xiàng)目B
C. 項(xiàng)目C
D. 所有三個(gè)項(xiàng)目會(huì)在同時(shí)完成
8. Based on the information in question 7, which will most likely be completed within time and
cost constraints?
A. Project A
B. Project B
C. Project C
D. Both A and B answers
在第七題的基礎(chǔ)下,哪個(gè)項(xiàng)目會(huì)在時(shí)間要求以及成本要求內(nèi)完成?
A. 項(xiàng)目A
B. 項(xiàng)目B
C. 項(xiàng)目C
D. A 和B
9. Cost budgeting can be best described by which of the following?
A. The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could occur during the project
B. The process of assembling and predicting costs of a project over its life cycle
C. The process of establishing budgets, standards, and a monitoring system by which the investment cost of the project can be measured and managed
D. The process of gathering, accumulating, analyzing, monitoring, reporting, an d managing the costs on an on-going basis.
下面哪個(gè)是對(duì)成本預(yù)算最合適的描述?
A. 制定未來發(fā)展趨勢(shì)以及評(píng)估項(xiàng)目中可能發(fā)生的概率、不確定性以及通貨膨脹的過程
B. 對(duì)項(xiàng)目在命周期中的成本進(jìn)行計(jì)算和預(yù)測(cè)的過程
C. 建立預(yù)算、標(biāo)準(zhǔn)和檢測(cè)系統(tǒng)以進(jìn)行對(duì)項(xiàng)目投資的衡量和管理的過程
D. 在項(xiàng)目進(jìn)行過程中收集、累計(jì)、分析、檢測(cè)、報(bào)告和管理成本的過程
10. Which of the following is a direct project cost?
A. Lighting and heating for the corporate office
B. Workers Compensation insurance
C. Piping for an irrigation project
D. A andB
下面哪一項(xiàng)是項(xiàng)目直接成本?
A. 公司辦公室的照明和取暖費(fèi)用
B. 職員的賠償保險(xiǎn)
C. 為一個(gè)灌溉項(xiàng)目裝管道
D. A 和B
PMP認(rèn)證考試題參考答案:6-10 BCCCC
閱讀本文的人還閱讀了:
1、PMP考試難嗎?
2、2014年P(guān)MP考試時(shí)間通知
3、PMP考試費(fèi)用是多少?
4、PMP認(rèn)證報(bào)名條件
5、PMBOK第五版6大變化