PMP試題1. Buyers use a variety of methods to provide incentives to a seller to complete work early or within certain contractually specified time frames. One such incentive is the use of liquidated damages. From the seller's perspective, liquidated damages are what form of incentive?
a. Positive
b. Negative
c. Nomi
d. Reverse
e. Risk-prone
買(mǎi)主使用各種方法以使承包商更早的或在某些契約指定時(shí)間框架內(nèi)完成工作。一種方式是清算賠償金的應(yīng)用,從承包商的觀點(diǎn)看,清算賠償金是那一種類(lèi)型的激勵(lì)?
a. 積極地
b. 消極地
c. 輕微地
d. 反面地
e. 風(fēng)險(xiǎn)傾向地
PMP試題2. Payment bonds are often required by the contract and require specific actions under the stated conditions. Payment bonds are specifically designed to ensure that the prime contractor provides payment of
a. Insurance premiums
b. Weekly payrolls
c. Incremental earnec
d. Subcontractors, laborers, and suppliers of material
e. Damages for accidents caused
在合同中通常需要付款保函,同時(shí)在所陳述的情況下需要采取特別措施。付款保函是專(zhuān)門(mén)用于保證為主要承包商提供什么樣的付款
a. 保險(xiǎn)費(fèi)
b. 每周的薪水
c. 增加所得
d. 轉(zhuǎn)包商、勞動(dòng)力和原料供應(yīng)l
e. 意外事故造成的損失
PMP試題4. The contracting function in an organization is considered to be decentralized when-
a. Each project manager has control over the contracting process for his or her project
b. The project manager controls contract award
c. The contracting person appointed to the project is available and under the project manager's direct control
d. Contracting is tailored to a single project
e. All above
在什么時(shí)候,組織內(nèi)合同的功能可以被分散考慮-
a. 每個(gè)項(xiàng)目經(jīng)理都他的/她的項(xiàng)目的合同程序
b. 項(xiàng)目經(jīng)理控制著合同的獎(jiǎng)勵(lì)
c. 在項(xiàng)目經(jīng)理的直接領(lǐng)導(dǎo)下,可用指定的項(xiàng)目合同人
d. 合同針對(duì)單個(gè)項(xiàng)目
e. 上述所有
PMP試題5. Which of the following terms represents a contract type category?
a. Fixed-price
b. Cost-reimbursement
c. Unit-price
d. a & b
e. a, b, & c
下列那一個(gè)描述了合同的類(lèi)型?
a. 固定價(jià)
b. 成本補(bǔ)償
c. 單元價(jià)
d. a 和 b
e. a, b, 和 c